The table shows the profit and loss analysis as well as the cashflow situation of the Accounting Software Project.
| No. | Name | Scenario | Total EUR | 2005 | 2006 | ||||||||||
| Okt | Nov | Dez | Jan | Feb | Mär | Apr | Mai | Jun | Jul | Aug | Sep | ||||
| 1. | Costs | Plan | 132,225 | 24,000 | 24,000 | 21,075 | 19,800 | 13,500 | 16,275 | 10,575 | 3,000 | 0 | 0 | 0 | 0 |
| Delayed | 138,225 | 24,000 | 24,000 | 21,075 | 19,800 | 13,500 | 13,800 | 19,050 | 3,000 | 0 | 0 | 0 | 0 | ||
| Total Costs | Plan | 132,225 | 24,000 | 48,000 | 69,075 | 88,875 | 102,375 | 118,650 | 129,225 | 132,225 | 132,225 | 132,225 | 132,225 | 132,225 | |
| Delayed | 138,225 | 24,000 | 48,000 | 69,075 | 88,875 | 102,375 | 116,175 | 135,225 | 138,225 | 138,225 | 138,225 | 138,225 | 138,225 | ||
| 2. | Payments | Plan | 86,000 | 33,000 | 0 | 13,000 | 0 | 13,000 | 0 | 0 | 13,000 | 0 | 0 | 14,000 | 0 |
| Delayed | 86,000 | 33,000 | 0 | 13,000 | 0 | 0 | 0 | 13,000 | 13,000 | 0 | 0 | 14,000 | 0 | ||
| Total Revenues | Plan | 86,000 | 33,000 | 33,000 | 46,000 | 46,000 | 59,000 | 59,000 | 59,000 | 72,000 | 72,000 | 72,000 | 86,000 | 86,000 | |
| Delayed | 86,000 | 33,000 | 33,000 | 46,000 | 46,000 | 46,000 | 46,000 | 59,000 | 72,000 | 72,000 | 72,000 | 86,000 | 86,000 | ||
| Total | Plan | (46,225) | 9,000 | (15,000) | (23,075) | (42,875) | (43,375) | (59,650) | (70,225) | (60,225) | (60,225) | (60,225) | (46,225) | (46,225) | |
| Delayed | (52,225) | 9,000 | (15,000) | (23,075) | (42,875) | (56,375) | (70,175) | (76,225) | (66,225) | (66,225) | (66,225) | (52,225) | (52,225) | ||
Version 6 - Created on 2005-11-19 with TaskJuggler v2.1.1